How Long a Kitchen Fit Really Takes
The real sequence of a kitchen installation stage by stage, what creates the worktop gap in the middle, and what quietly pushes a fit past its schedule.
8 min readTeesside Premium
The one-minute version
"How long does it take to fit a kitchen" is the question people ask straight after price, and it is the harder of the two to answer honestly. A kitchen is not one job. It is six trades running in a fixed order, where each one is held in place by the one before it, and none of them can be pulled forward to fill a gap in the diary.
So the answer worth having is not a number of days. It is the sequence, plus the two points in it where the clock stops belonging to your fitter: the worktop fabrication gap, and whatever the old kitchen was hiding. Get both written into a schedule and you can plan a household around the job. Take a day count over the phone from somebody who has not stood in the room, and you are planning around a guess.
What actually happens, and in what order
Survey and measure. Somebody measures the room as it was built rather than as the supplier drew it. Skipping this is what turns a schedule into fiction.
Delivery check. Every item counted against the plan while there is still time to get a replacement sent, and before the old kitchen is in a skip.
Gas cap-off. A Gas Safe registered engineer isolates the hob. Nothing comes out until that has happened.
Strip-out and disposal. Old units, old tops, old tiling, out and gone. This is also the moment the house tells you what it has been hiding.
First fix. Water, waste and cable run for the new layout, buried in walls and floors. Everything after this is expensive to change.
Making good. Chases filled, holes patched, boxing built. Fresh plaster has to dry before anything gets decorated over it.
Base units. Levelled off the floor as it actually falls, not off the old worktop, then scribed to walls that in most older Teesside houses are not straight and have moved since they were built.
Worktop template. A templater measures the units where they now stand. On laminate the top is cut and jointed in the room instead, and this stage disappears.
The gap. On stone, quartz and solid surface, the top is fabricated off site. Base units in, no worktop, no sink, no hob.
Worktop fit, sink and hob. The top lands, cut-outs and all. This is the day running water comes back.
Second fix. Taps, waste, appliances, sockets and switches live, hob recommissioned by a Gas Safe registered engineer.
Tiling, decoration and snagging. Splashbacks, walls and ceilings, then the list of small things you only notice once the room is quiet.
That is the order, not a timetable. The stages are short at the front and long in the middle, and how long it takes to fit a kitchen turns mostly on how much of that middle happens off site rather than in your house.
Why the worktop shapes the whole week
Because a hard worktop cannot be measured in advance. Quartz, granite and solid surface are templated after the base units are standing in their finished position, then cut and polished by a fabricator who has other kitchens in front of yours. That is a real pause with a real cause, and it is the part of the programme your fitter has the least control over.
Laminate has no pause. It is cut and jointed on site, so the sink can go back the same week the units do. Solid wood sits in between: cut in the room, but it wants oiling before and after, and that is drying time nobody can compress.
The practical move is to ask your supplier for the template-to-fit lead time in writing when you order, and to ask again if your order date slips, because the fabrication queue moves with the season. Choose the material against your deadline as well as against the room. If the kitchen has to be usable by a fixed date, laminate buys you that date outright. The kitchen fitting page sets out how each surface behaves once it is in.
Two of the commonest stretches are notifiable rather than optional. A new circuit or a board change — usually an induction hob — is notifiable under Part P and certified by a registered electrician. Moving the sink is altered drainage, which makes it building regulations work. Extraction over a relocated hob is sized by Approved Document F, and taking out a wall between two rooms is structural, needing approval and, on a semi or terrace, a party wall notice.
What stretches a fit beyond its schedule
Almost every overrun traces back to one of a short list, and most of the list is findable at survey rather than on the day.
| What adds time | Why it adds time | Findable before you start? |
|---|---|---|
| Moving the sink or waste | The new run needs fall back to the stack; a solid ground floor may mean lifting screed | Yes, at survey |
| Moving the hob or cooker point | The gas run has to be extended and tested by a Gas Safe registered engineer | Yes, at survey |
| An induction hob on an old cooker circuit | A new circuit is notifiable work in England under Part P, so it is self-certified by a registered competent person, certified by a registered third party, or notified to building control before it starts | Yes, at survey |
| An extractor that has to be ducted outside | Approved Document F puts the minimum intermittent extract rate for a kitchen at 30 litres per second where a cooker hood extracts to the outside, and 60 where there is no hood or the hood does not extract outside, so the duct route has to exist before the design is fixed | Yes, at survey |
| Walls out of square, floors out of level | Every unit gets scribed and packed individually instead of dropped in | Partly. Older houses are a fair bet |
| Fresh plaster after first fix | Skim has to dry before it is decorated, and it dries at its own pace | Yes |
| A pre-2000 textured ceiling or old floor tiles | May contain asbestos, which stops a dry strip-out until it is tested and handled properly | Yes, by testing first |
| A short or damaged delivery | The replacement arrives at the supplier's speed, not yours | Yes, by checking the boxes |
The last row is the one that catches most people, and it is free to prevent. Our own electricians and Gas Safe registered engineers price the first four rows into the quote at survey, so they arrive as a line you agreed rather than a phone call halfway through.
The things customers do that add a week
Nearly every customer-side delay is a decision left open. That is not a criticism. Nobody buys a kitchen often enough to know which decisions are load-bearing, so here are the ones that are.
Changing the layout after the survey. The measurements, the first fix and often the order all follow the layout. Move the sink a metre after the plan is signed and three stages have to be redone on paper before anything happens in the room.
Buying appliances late. Integrated appliances have specific apertures. A dishwasher chosen after the units are ordered is a decision made in the wrong order, and the housing is the thing that has to change.
Leaving the worktop material open. Deciding between laminate and quartz late does not delay the template. It delays the whole back half of the job, because one of those choices has a fabrication queue attached and the other does not.
Adding work while we are there. Flooring, a knock-through, a radiator moved. All reasonable, all cheaper to do now than later, and all needing time added rather than absorbed. Ask at survey, not on day three.
Being unreachable for the template. Somebody has to confirm overhang, upstand and cut-outs. A day spent waiting for that answer is a day.
Getting a schedule you can actually plan around
We will not put a day count on a kitchen nobody has measured, and we will not promise a finish date built around a delivery that has not landed. If you want a stone top and a finished kitchen inside a few days, we are the wrong firm, because the fabrication is not ours to hurry. What you get instead is a fixed written price, a stage-by-stage schedule with the worktop gap marked on it, and a written variation with a price attached before anything found behind the old units gets done.
If you are working to a hard date, say so at the survey. That is when the material choice can still change. See how a fit runs in Middlesbrough, or, if the kitchen is in a rented property and the clock is a void period rather than a family, the between-tenancy checklist covers how it fits around everything else that has to happen in a turnaround. Send us the plan through our contact page and we will tell you what your room does to the sequence.